High Performance Building
Last Update: 07/08/06 ehb
http://www.ferreiragroup.com/31Tannery/31Tannery-Summary-062206.pdf
5/12/06 Solar PV inverters uncrated and moved into electrical inverter room
All solar panels mounted on roof (1276 Sharp 175's)
Combiner box connections underway
Solar DHW piping completed in mechnical room and routed to roof, awaiting replacement panels damaged in shipment? Roof penetration on hold.